Contract obligation extraction

What should AI extract when a contract says “30 days after go-live”?

AI obligation extraction can capture a promise before anyone knows its due date. If a baseline report is due 30 days after written acceptance, save the deliverable and interval now. Use the forecast to chase the acceptance that will start the clock. Use AI contract data extraction to capture the words that start the clock, including who must accept the work and how.

Get the worksheet
Worked exampleWhen the reporting clock starts
September 1
Forecast launch
September 8
Written acceptance
October 8
Baseline report due

The buyer’s written acceptance starts the 30 calendar days. Use the forecast to chase the evidence.

Key takeaways

  • Written acceptance on September 8 supplies the trigger that the August extraction run could not see.
  • Using the September 1 forecast would make the report appear due one week early.
  • The October 6 email documents delivery. The verifier still needs to check the three required metrics.

How do you track an obligation when the event that starts the clock has not happened?

Plover Labs has three possible “launch dates” in its fictional rollout file. Staff attended training August 26. The project plan forecast September 1. On September 8, the buyer accepted the production launch in writing. The contract defines that written acceptance as go-live and gives the supplier 30 calendar days to deliver a performance baseline.

An AI import in August can extract the obligation and its trigger. Entering the September 1 forecast as an actual event would produce an October 1 deadline. The buyer’s September 8 acceptance makes the deadline October 8. When the supplier emails the report on October 6, the first calendar would show it five days late. The signed rule puts delivery two days early.

Extract the entire promise

Ask the reviewer for the deliverable, who owes it, defined trigger, unit of time, and source section. Include any definition or exhibit that explains the trigger. Capture a short quotation in the owner's work record. The label “baseline report” is too sparse for a colleague to decide whether a slide deck or a signed measurement package satisfies the requirement.

Which milestones change the obligation?

Trigger evidenceSource event or missing proofDecision or next action
ForecastSeptember 1 in project planSchedule internal follow-up
TriggerWritten acceptance dated September 8Calculate October 8 in this example
DeliveryReport emailed October 6Verify required baseline metrics
Keep the forecast, acceptance, and delivered report as separate pieces of evidence.

Give someone the job of obtaining acceptance

Assign the implementation manager a follow-up at the forecast launch. The task is to ask the buyer for dated acceptance covering this rollout. If acceptance has yet to arrive, reschedule the evidence check and leave the report date open. This gives the manager something to do without presenting a guess as a contractual deadline.

Calculate from the confirmed event

Check who issued the acceptance and which rollout it covers. Record its effective date, then reproduce the calculation against the wording. If different facilities have independent launches, split the commitment into records the facilities can verify. Keeping the source and evidence together makes a later correction much easier to explain to the supplier.

Define what closes the work

In ContraxAware, use the obligation owner, timing, source wording, and evidence to document the handoff. The supplier's email on October 6 may establish delivery. Name a separate verifier if the business needs to check that the report includes all three required metrics. Keep the delivery date and the verifier's conclusion available for the next service review.

Record the event that starts the clock

Open the obligation in Contract Map. Have the owner attach the dated acceptance and record the calculation. Ask another colleague to find both in the contract management system before relying on an overdue report.

This guide to verifying the source of a contract date walks through the evidence check.

Teams that track contract obligations in Contract Map can attach the written acceptance to the report obligation. When reviewing dates and renewals, use that acceptance date to check the first report deadline.

For the full workflow, read how to assign obligation owners and verify completion.

A quarterly report has a September 1 deadline. The onboarding report below it says to record the actual signing date first.View full-size screenshot
The Northstar onboarding clock starts at signing. Plover’s clock starts at written acceptance. In either case, keep the trigger visible so the person scheduling the report knows which evidence to obtain.
Excel worksheet

Conditional obligation and trigger evidence worksheet

Classify each milestone, locate written acceptance, then calculate the report deadline and assign someone to verify the delivered metrics.

Preview a completed worksheet row
Event or deliverable
Team training
Evidence
Attendance record
Date in sample
2027-08-26
Role in timeline
Preparation milestone
Date calculation
No contractual deadline starts
Owner
Training coordinator
Decision or action
Retain training evidence; continue monitoring for written go-live acceptance.
Download the worksheet (.xlsx)

Try an event-based obligation

Trace one event-based obligation from the source clause to the person who verifies completion.

Frequently asked questions

What should an AI-generated task show before acceptance?

A named owner, a pending trigger, the interval, and the evidence needed to establish the date. A useful result explicitly identifies the piece of information that is still missing.

What if the buyer and supplier disagree about go-live?

Keep both accounts and their supporting records. Ask the authorized business owner and counsel to resolve which event the agreement recognizes before issuing an overdue finding.

What if separate sites go live on different dates?

Read whether each site's acceptance creates a separate reporting commitment. If it does, assign each site a source, acceptance record, owner and due date.

Which date should an executive dashboard show?

Distinguish open commitments awaiting a trigger from currently scheduled obligations. Put the owner and next evidence check beside a pending item so the team can still act.